. Project Planning and Preparation
Milestone 1: Finalizing Research Plan and Methodology
- Date: Week 1-2
- Tasks:
- Finalize the overall research plan, including objectives, sampling strategy, and research tools (surveys, interviews).
- Develop detailed timelines and assign responsibilities.
- Confirm stakeholder engagement strategy and outreach plans to educational institutions and relevant partners.
2. Survey and Interview Development
Milestone 2: Completion of Survey and Interview Templates
- Date: Week 3
- Tasks:
- Design survey questionnaires and interview templates based on the identified research focus areas.
- Pilot test the surveys and interview templates with a small group to ensure clarity, relevance, and ease of completion.
- Revise based on feedback from the pilot test.
3. Data Collection
Milestone 3: Launch of Data Collection Phase
- Date: Week 4-6
- Tasks:
- Begin distributing surveys to the selected student population (500 respondents across institutions).
- Conduct interviews and focus groups with key stakeholders, faculty members, and students.
- Ensure online and offline methods are used for diverse data collection.
- Continue regular monitoring to ensure data collection is progressing as planned.
Milestone 4: Data Collection Complete
- Date: Week 8
- Tasks:
- Ensure a sufficient sample size (500 students) has been reached.
- Close the survey and interview data collection channels.
- Begin preliminary data cleaning and review to ensure completeness and accuracy.
4. Data Coding and Analysis
Milestone 5: Completion of Data Coding and Categorization
- Date: Week 9-10
- Tasks:
- Code qualitative data from interviews and open-ended survey responses.
- Categorize the data according to the identified educational need areas (academic support, technological access, mental health resources, financial support, etc.).
- Review for any trends or patterns in the data that can inform the Student Need Index.
Milestone 6: Data Analysis and Index Creation
- Date: Week 11-12
- Tasks:
- Analyze the data to identify key trends, correlations, and gaps in student needs.
- Develop the Student Need Index (SNI), determining the weight and importance of various student needs based on the intensity and urgency of responses.
- Validate the SNI methodology with academic advisors, key stakeholders, and experts.
5. Report Writing and Stakeholder Engagement
Milestone 7: First Draft of Research Report
- Date: Week 13
- Tasks:
- Compile the data analysis, index development, and overall findings into a comprehensive report.
- Draft the report, including a detailed explanation of the methodology, results, and implications for future educational initiatives.
- Include actionable recommendations for SayPro’s educational strategies.
Milestone 8: Stakeholder Review and Feedback
- Date: Week 14
- Tasks:
- Share the first draft with key stakeholders (educational institutions, NGOs, student groups, etc.) for feedback.
- Collect feedback on the report’s accuracy, clarity, and applicability.
- Revise the report based on the feedback received.
6. Final Reporting and Dissemination
Milestone 9: Final Report Submission and Presentation
- Date: Week 15
- Tasks:
- Finalize the report, incorporating all revisions from stakeholder feedback.
- Present the findings, index, and recommendations to SayPro’s leadership, partner institutions, and key stakeholders.
- Create an executive summary for wider dissemination.
Milestone 10: Public Release of Findings
- Date: Week 16
- Tasks:
- Publish the full report and executive summary on SayPro’s website.
- Share the findings through webinars, social media, and other communication channels to ensure widespread access to the results.
- Host a follow-up session or webinar to discuss the findings and next steps.
7. Ongoing Monitoring and Updates
Milestone 11: Establishment of Tracking System for SNI
- Date: Week 17 onwards
- Tasks:
- Develop a system for tracking changes in the Student Need Index over time.
- Set up regular review periods (quarterly, annually) to update the index based on new data and shifting student needs.
- Regularly engage with stakeholders to keep the research relevant and responsive to emerging trends.
Timeline Overview
Milestone | Timeline |
---|---|
1. Finalizing Research Plan and Methodology | Week 1-2 |
2. Completion of Survey and Interview Templates | Week 3 |
3. Launch of Data Collection Phase | Week 4-6 |
4. Data Collection Complete | Week 8 |
5. Completion of Data Coding and Categorization | Week 9-10 |
6. Data Analysis and Index Creation | Week 11-12 |
7. First Draft of Research Report | Week 13 |
8. Stakeholder Review and Feedback | Week 14 |
9. Final Report Submission and Presentation | Week 15 |
10. Public Release of Findings | Week 16 |
11. Establishment of Tracking System for SNI | Week 17 onwards |